|
Archived Documents:
Major Scheme Appraisal in Local Transport Plans Part 1: Detailed Guidance on Public Transport and Highways Schemes
Version 3: 4 April 2003
Annex C: Risk analysis
C1. All investment schemes are
exposed to risk. Most risks will be common
to conventional public sector procurement
and the Private Finance Initiative (PFI).
The appraisal must contain an assessment of
risk, irrespective of which procurement route
may eventually be chosen. The LTP guidance
makes clear that "decisions on the acceptability
of major schemes are taken prior to any consideration
of the possible funding route".[47]
The Department expects to see a full assessment
of risk for all major schemes. Where there
are major risks, promoters will have to demonstrate
that such risks are understood and can be
actively managed within the public sector
or transferred at an appropriate cost to the
private sector.
C2. The full requirements for
a risk assessment are detailed in Treasury
Taskforce (1999) Technical Note 5 "How to
Construct a Public Sector Comparator". Annex
4 of H.M. Treasury (2003) "Green Book" provides
further guidance on quantifying and clarifying
risk. Part 4 of the Highways Agency's "Value
for Money" manual provides guidance on risk
analysis for highway schemes.
C3. For smaller schemes, a more
simplified set of procedures may be used.
The key issues in assessing risk in all cases
are:
- the range of possible outcomes;
- the probability of each outcome;
and
- the interactions between
different elements which affect outcomes.
C4. Although a range of outcomes
for any one element of the appraisal may be
relatively easy to determine, say through
modelled sensitivity or observed outcomes
of similar schemes, attaching detailed probabilities
to these outcomes is much more problematic.
Providing detailed correlation between different
elements of the appraisal is also very difficult
since there is a wide range of causal and
dependent relationships affecting costs, traffic
levels / patronage, revenues and benefits
of the scheme. For example, there may be linkages
between low levels of traffic / patronage
and the possibilities of reduced operating
or maintenance costs.
C5. Promoters should undertake
a three-stage process for all major schemes.
The level of detail required will need to
be discussed with the Department. As a general
rule the amount of time and resources that
are devoted to quantifying risks should relate
to their likely materiality.
Step 1: Prepare
a risk register of the main risks likely to
affect the delivery and operation of the scheme.
The risk register should start from construction
risk, from timescale and cost perspectives,
and then move onto operational risks and factors
likely to affect traffic / patronage, revenues
and delivery of scheme benefits. The Department
may be able to offer some further indication
of areas to consider, drawing on the outcomes
from recent major schemes. The risk register
should be included with the appraisal document.
Step 2: Assess
a range of possible outcomes that may occur
due to combinations or different levels of
the risks identified in the risk register.
This may be possible through modelled sensitivity
analysis or observed outcomes from similar
schemes. If using sensitivity analysis, then
combinations of sensitivity tests should be
used to examine potential interactions between
key underlying factors. In this way some of
the implicit relationships between individual
risk elements are considered.
The range of outcomes should
consider both the upper and lower extremes
of the possible range, taking into account
any reasonable constraints. Constraints may
include system capacity on maximum patronage
estimates. These constraints would be expected
to place an upper bound on patronage and revenue
estimates.
Step 3:
Assess the likelihood of occurrence for each
of the possible outcomes. For smaller schemes
it may be acceptable to assess the probability
of any one outcome occurring using a simple
four-point scale, expanded to more levels
if appropriate. This scale would use, at a
minimum, very unlikely, moderately unlikely,
unlikely or most likely, where the most likely
outcome would normally be the central forecast
value. For larger major schemes the Department
needs to see a full account of risk to be
taken with a thorough Quantified Risk Assessment
(QRA).[48]
This assessment of risk should be based on
numerical probabilities. These probabilities
allow expected values and the variation around
these values to be developed.[49]
Operating costs, capital costs and benefits
should all be based on expected values. The
probabilities applied to each outcome will
be a matter of some judgement, but will require
justification. In general, it is expected
that the distribution of cost will be skewed
towards increasing costs whilst the patronage
and revenue distributions would be skewed
downwards.
C6. It is essential that the
risk assessment is clear and comprehensive,
it helps move the optimism bias adjustment
from its upper bound level toward its lower
bound. The exact mechanism of how this works
is explored in the next section. Also this
risk assessment will be reviewed as part of
the technical audit of some larger schemes.
C7. It is also important that
promoters consider how the individually outlined
risks will be managed. Evidence of this consideration
and the approach to risk management must be
presented within the appraisal submission.
[47]
DETR (2001) Guidance on Full Local Transport
Plans, Paragraph 71.
[48] Larger
schemes will typically be those in excess
of £20m. Promoters should consult the Department
to determine if a QRA for their scheme will
be necessary.
[49] The expected
value is defined as the average of all possible
outcomes, taking account of the different
probabilities of those outcomes occurring.
The expected outcome is also known as the
"mean" or "unbiased" outcome. It is generally
not the same as either the "planned" or "most
likely" outcome. The most likely outcome is
that which has the highest probability of
occurring.
Published: 2 May 2003 | Updated: 12 May 2003
[ Previous ] [ Contents ] [ Next ]
|