|
Archived Documents:
Major Scheme Appraisal in Local Transport Plans Part 1: Detailed Guidance on Public Transport and Highways Schemes
Version 3: 4 April 2003
Annex D: Optimism bias
D1. Optimism bias is the demonstrated
tendency for appraisers to be over-optimistic
about key project parameters. It must be accounted
for explicitly in all appraisals, and can
arise in relation (but not exclusively) to:
- capital costs;
- works duration;
- patronage / benefits.
Capital costs
D2. Optimism bias uplifts need
to be applied to the expected capital cost
of an option. This applies even where a full
quantified risk analysis has been carried
out. The aim of this approach is to provide
better estimates of the final cost of a proposal
at key stages in its development. This should
benefit both promoters and assessors of a
scheme alike. The type of project, its stage
of development, and the extent of risk management
determines the levels of optimism bias uplifts.
Types of project
D3. Typically schemes which
involve unusual construction techniques or
innovative technologies will have larger uplifts
than standard civil engineering schemes. The
categorisation of particular schemes is still
under discussion within the Department. Expert
advice is currently been sought on this and
will be made publicly available. In the interim,
the values from the Mott McDonald report provide
an indication of possible uplifts to schemes.[50]
However it should be noted that these values
are purely illustrative. As a guide examples
of non-standard types of engineering may include
light rail schemes or guided bus. Standard
civil engineering would more likely cover
standard road schemes, and bus priority schemes.
A further category of standard buildings may
be appropriate for bus stations and some elements
of park and ride.
Stages of development
D4. The size of the optimism
bias adjustment required will reduce as project
definition improves and / or as risks are
identified and taken into account. In practice,
reductions will be linked to formal stages
in the development of projects. For example,
for highway schemes, reductions will be specified
at public consultation / preferred route,
order publication and works commitment stages.
For public transport schemes the specific
stages of reduction in optimism bias are still
under discussion.
Risk management
D5. Where a QRA has been carried
out and project costs include an allowance
for risk, the size of the optimism bias adjustments
required will be further reduced.
Note, however, that allowance
for risk is not a complete substitute for
optimism bias adjustment.
Works duration
D6. Optimism bias can also occur
in the estimation of the construction period
of a scheme. This may result in higher costs
and a delay in the receipt of benefits. Potential
delays should be assessed and incorporated
into the risk assessment. Sensitivity tests
on costs (construction and disruption) and
benefits of a longer construction period should
be carried out.
Patronage / Benefits
D7. The evidence for benefits
optimism bias in the transport sector is unclear,
however there is a perception that optimism
bias may be an important issue. Thus, the
Department recommends that optimism bias in
this area should be considered by developing
central, optimistic and pessimistic scenarios.
In some cases, additional scenarios and /
or sensitivity tests may also be required,
to test the impact of key uncertainties. An
example of this may be regeneration benefits
of a scheme. These scenarios should cover
key areas of risk, particularly with regard
to patronage and demand assumptions.
D8. The Department is aware
that these investigations need to be proportionate
to the scheme scale, and is happy to discuss
with promoters the exact requirements in this
area.
[50]
Available from: http://www.hm-treasury.gov.uk.
Published: 2 May 2003 | Updated: 12 May 2003
[ Previous ] [ Contents ] [ Next ]
|