|
TAG Unit 2.6: Applying the Multi-Modal New Approach to Appraisal to Highway Schemes
February 2004
Unit 2.6 (Adobe Acrobat - 133kb)
1. Introduction
1.1 Scope
1.2 Recommended Software - Safety and Economy
2. DMRB and TAG Correspondence Tables
2.1 Introduction
2.2 Correspondence Tables
3. AST Appraisal Information
3.1 Background
3.2 Completing the AST
3.3 Option
3.4 Description
3.5 Problems
3.6 Present Value of Cost to Government
4. Further Information
5. References
6. Document Provenance
1. Introduction
1.1 Scope
1.1.1 Before reading this document, the reader should
refer to Trunk Roads: Applying the Multi-Modal New Approach
to Appraisal to Highway Schemes (TAG
Unit 1.3).
1.1.2
This document should be used for the following
types of initiative:
- all Highways Agency capital improvement projects;
- all Local Authority highway schemes in England, with
capital costs in excess of £5 million, Local Authorities
should also refer to Major Scheme Appraisal in Local
Transport Plans: Detailed Guidance on Public Transport and
Highway Schemes (TAG Unit 1.4) for additional advice;
- schemes located in England only.
1.1.3
This document should not be used for the following
types of initiative:
- schemes located in Northern Ireland, Scotland or Wales
- unless the project sponsor indicates otherwise;
- Multi-Modal studies - TAG accompanied by TUBA software
and manuals (see below) should be used;
- Regional Transport Strategies - refer to PPG 11;
- Local Transport Plans - see Guidance on Full Local
Transport Plans (DfT, periodically updated)
- Major public transport schemes - the reference for this
is Major Scheme Appraisal in Local Transport Plans:
Detailed Guidance on Public Transport and Highway Schemes
(TAG Unit 1.4).
1.2 Recommended
Software - Safety and Economy
1.2.1
In order to appraise multi-modal projects,
and to identify all groups that benefit and those that not
associated with a scheme, the way in which transport cost
benefit analysis is reported has been adapted. Furthermore,
1998 is now the price base (formerly 1994). These changes
do not affect the fundamental principles of appraisal, merely
the presentation of results. (Since the software recommended
in this section incorporates these changes, it is not
necessary for the analyst to understand the background
to the changes. However, The Economy Objective
(TAG
Unit 3.5) provides a discussion of the issues involved.)
1.2.2
This document recommends the use of one, or
both, programs:
| Software |
Capabilities of the Software
|
| PVB for Transport Economic Efficiency |
PVB for Accidents |
| COBA11 |
fixed trip matrix only |
fixed trip matrix variable trip matrix |
| TUBA |
fixed trip matrix variable trip matrix |
not included in program |
1.2.3
Neither COBA10 nor URECA (discontinued) provides
appropriate outputs for input into the Transport Economic
Efficiency tables. However, COBA10 data will run on COBA11,
thus updating existing analyses should not present any major
problems.
In addition, QUADRO software may be used for the calculation
of accidents and Transport Economic Efficiency during construction
and future maintenance.
2. DMRB and TAG Correspondence Tables
2.1 Introduction
2.1.1
This document is focused on the production
of a NATA appraisal at Plan Level equivalent to a DMRB Stage
3 assessment. This assumes a high level of detail can be achieved
and the information available from the DMRB assessment is
of an appropriate level of detail. However, less detailed
information is available at DMRB Stages 1 and 2, thus the
NATA appraisal method will need to reflect this and it is
likely that assumptions will need to be made as appropriate.
Where this is necessary, analysts should bear in mind the
NATA principle that judgement should be based on evidence
where possible and should ensure that all assumptions are
justifiable and fully documented. Some advice with regard
to Stage 1 and 2 appraisals, is given in the TAG Units covering
each of the sub-objectives in the AST.
The Appraisal Summary Table (AST) is given
in TAG
Unit 2.7.2. The AST is a one-page summary of the effects
of a scheme/Plan for use by decision-makers, explained further
in Section 3.
2.2 Correspondence
Tables
2.2.1
To assist the analyst, a correspondence table
has been produced for the Environment Objective (Table 1),
which illustrates for each sub-objective the worksheets that
need to be completed as part of the GOMMMS appraisal and the
source of the information from the DMRB assessment and other
related sources, where there is a relevant equivalence. For
those sub-objectives that are introduced by the New Approach
To Appraisal, there is no equivalence in DMRB.
2.2.2 Tables 2 to 5 provide the correspondence tables for the Safety, Economy, Accessibility and Integration Objectives respectively, including references to other sources of information than DMRB where relevant.
Table 1: TAG - DMRB Volume 11 Correspondence Table for Environment
| TAG Environment Sub-objective |
TAG Worksheet (Plan Level) |
DMRB Sections and Related
Sources of Information |
| Noise |
W1 (TAG
Unit 3.3.2) |
Section 3 Part 7 (August
1994) 'Noise'
Ref. to DMRB Volume 11 Section 3.7 - noise annoyance
relationship |
| Local Air Quality |
W1 (TAG
Unit 3.3.3) |
Section 3 Part 1 (February 2003) 'Air Quality' |
| Greenhouse Gases |
W1 (TAG
Unit 3.3.4) |
Section 3 Part 1 (February 2003) 'Air Quality' |
| Landscape |
W1 (TAG
Unit 3.3.7) |
Section 3 Part 5 (June
1993) 'Landscape Effects'
Ref. to DMRB Volume 11 Section 3.5.3 - methodology |
| Townscape |
W1 (TAG
Unit 3.3.8) |
Section 3 Part 2 (August
1993) 'Landscape Effects'
Ref. to DMRB Volume 11 Section 3.5.8 - methodology |
| Heritage of Historic Resources |
W1 (TAG
Unit 3.3.9) |
Section 3 Part 2 (August
1994) 'Cultural Heritage'
Ref. to DMRB Volume 11 Section 3.2.6 - methodology |
| Biodiversity |
W1 (TAG
Unit 3.3.10) |
Section 3 Part 4 (June
1993) 'Ecology and Nature Conservation' Ref. 11.3.4.5
Section 3 Part 11 (June 1993) 'Geology and Soils' Ref.
11.3.11.5 |
| Water Environment |
W1 (TAG
Unit 3.3.11) |
Section 3 Part 10 (August
1998) 'Water Quality and Drainage' |
| Physical Fitness |
W1 (TAG
Unit 3.3.12) |
Section 3 Part 8 (June
1993) 'Pedestrians, Cyclists, Equestrians and Community
Effects'. Ref. Changes in journey time |
| Journey Ambience |
W1 (TAG
Unit 3.3.13) |
Section 3 Part 9 (June
1993) 'Vehicle Travellers'
Ref. Driver Stress and View from the Road |
Table 2: TAG - DMRB Correspondence Table for Safety
| TAG Safety Sub-objective |
TAG Worksheet (Plan Level) |
DMRB Sections and Related
Sources of Information |
| Accidents |
See note 1 |
Methodology - DMRB13.1
and DMRB14
Parameters - Interim COBA Guidance (ICG) |
| Security |
W1 (TAG
Unit 3.4.2) |
None (refer to TAG
Unit 3.4.2) |
Note 1 - No worksheet contained in TAG, but a suitable worksheet
may be adapted from GNATA Worksheet 7.1.
Table 3: TAG -DMRB Correspondence Table for Economy
| TAG Economy Sub-objective |
TAG Worksheet (Plan Level) |
DMRB Sections and Related
Sources of Information |
| Public Accounts |
None |
None - refer to
TAG Unit 3.5.1 |
| Transport Economic Efficiency |
W1 (TAG
Unit 3.5.2) |
None - refer to TAG
Unit 3.5.3 |
| Reliability |
None |
None - refer to TAG
Unit 3.5.7 |
| Wider Economic Impacts |
W1 (TAG
Unit 3.5.8) |
None refer to TAG Unit 3.5.8 |
Table 4: TAG - DMRB Correspondence Table for Accessibility
| TAG Accessibility Sub-Objective |
TAG Worksheet (Plan Level) |
DMRB Sections and Related
Sources of Information |
| Option Values |
None |
None - refer to TAG
Unit 3.6.1 |
| Severance |
W1 (TAG
Unit 3.6.2) |
Methodology - refer to
DMRB 11.3.8
Assessment guidelines - refer to
TAG Unit 3.6.2 |
| Access to Transport System |
None |
None - refer to TAG
Unit 3.6.3 |
Table 5: TAG -DMRB Correspondence Table for Integration
| TAG Accessibility Sub-Objective |
TAG Worksheet (Plan Level) |
DMRB Sections and Related
Sources of Information |
| Transport Interchange |
W1 (TAG
Unit 3.7.1)
W2 (TAG
Unit 3.7.1) |
None - refer toTAG
Unit 3.7.1
None - refer toTAG
Unit 3.7.1 |
| Land-use Policy |
W1 (TAG
Unit 3.7.2) |
DMRB 11.3.12 |
| Other Government Policies |
W1 (TAG
Unit 3.7.3) |
None refer to TAG
Unit 3.7.3 |
3 AST Appraisal Information
3.1 Background
At the heart of New Approach To Appraisal process
is the Appraisal Summary Table (AST). This records the degree
to which the five Central Government objectives for transport
(environment, safety, economy, accessibility and integration)
would be achieved and provides a comprehensive summary of
the impacts of an option. It is intended that assessors (decision-makers)
should use the information provided in the AST (and, where
necessary, its more detailed supporting documents) to make
a judgement about the overall value for money of the option.
3.1.1
The assessment of the overall value of an option
from the AST is one of four assessment strands. The others are:
- achievement of local and regional objectives;
- amelioration of problems; and
- supporting analyses of distribution and equity, affordability
and financial sustainability, practicality and public acceptability,
and impacts on 10 Year Plan targets.
3.1.2
The appraisal processes under each of these
other three strands are explained in The Appraisal Process
(TAG Unit 2.5).
That document also contains advice on the procedure for distilling
the information from all four appraisal strands and making
recommendations. The appraisal of highway projects should
include all four appraisal strands, it should not be restricted
to the AST alone.
3.1.3
Guidance on appraising the achievement of
local and regional objectives is summarised in The Appraisal
Process (TAG
Unit 2.5). Although it is convenient to use the five Central
Government objectives to structure local and regional objectives,
the indicators associated with local and regional objectives
should be much more specific to the scheme's context (e.g.
relief of congestion would only serve to duplicate the AST
entry).
3.1.4
Amelioration of problems, see The Appraisal
Process (TAG
Unit 2.5), relates to the contribution of the improvement
to pre-defined measures of performance.
3.1.5
Supporting analyses relate to four areas. The
Appraisal Process (TAG
Unit 2.5) provides further detail. For distribution and
equity, the supporting analysis provides a breakdown of a
subset of the entries in the AST, generally on a spatial basis.
For affordability and financial sustainability, since the
financial impact of highway schemes usually relates to public
sector institutions, the GOMMMS affordability and financial
sustainability tables need not be completed; the COBA manual,
provides the format for the presentation of a cost calculation
specific to road schemes. (Regardless of the software
used to calculate PVC - e.g. COBA or TUBA - this format
remains relevant.) For practicality and public acceptability, The Appraisal
Process (TAG
Unit 2.5) provides a checklist of issues that may be relevant.
For the impacts on the 10 Year Plan Targets, reference should
be made to TAG
Unit 3.8.2
3.2 Completing the AST
3.2.1
The following sections provide advice on how
to complete the AST, under each of the headers given in the
table. The Appraisal Process (TAG
Unit 2.1) provides further detail and should be referred
to. A copy of the AST can be found in TAG
Unit 2.7.2.
3.2.2
The AST provides a summary of the impacts of
an option and must be presented on a single sheet of paper.
A separate AST must be prepared for each option considered,
including rejected options. This will provide an audit trail
of the rejection of options during the appraisal process and
support for the selected preferred option. Each option should
be distinct and a 'real' option, not simply a variation or
modification. Where an entry using the terms "not assessed"
or "not applicable" is made in the AST, there needs
to be an explanation of why these terms have been used.
3.3 Option
3.3.1
This box should be completed with the option
number.
3.4 Description
3.4.1
A few key words of text should be inserted
which summarise the main thrust of the option. This may not
be able to adequately express all the interventions involved,
in which case a supplementary single sheet should be included
giving a complete specification of the option.
3.5 Problems
3.5.1
This box should summarise the problems in the
base year and in the do-minimum transport system in the forecast
year, also the changes in the forecast year problems that
would be brought about by the option. The definition of a
problem should focus not on the symptoms of a problem
(e.g. congestion through the village) but on the causes
of a problem (e.g. congestion due to an factory or school
or a bottleneck elsewhere). These causes influence the type
of solution required. Emphasising the causes allows other
modes to be considered, as well as different scales of intervention
that may provide the more feasible and appropriate solution
to the problem. In each case, only key points should be summarised
(reference can be made to other reports for the specific details).
3.5.2
Specific entries in the Problem box should include:
- an outline of the causes of the problems on the road;
- an indication of the status and function (importance)
of the route (e.g. Trans European, major port or conurbation
link, city orbital);
- the number of vehicles per day; and
- the percentage of HGV (this should always be stated for
bypass projects)
3.6 Present
Value of Cost to Government
3.6.1
For most road schemes, capital and operating
costs will relate exclusively to government expenditures.
In such circumstances, "Present Value Cost to Government"
may be simplified to "Present Value Cost £m".
Note, however, that where this is not the case, then the format
used in TAG should be used.
3.6.2 The PVC should be in 1998 market prices, discounted to 1998.
4. Further Information
The following documents provide information that follows on directly from the key topics covered in this TAG Unit.
| For information on: |
See: |
TAG Unit number: |
| Highway Schemes |
Trunk Roads: Applying the Multi-Modal New Approach
to Appraisal to Highway Schemes |
TAG
Unit 1.3 |
| Appraising transport schemes
against the Government's 5 objectives for transport |
The Environment Objective
The Safety Objective
The Economy Objective
The Accessibility Objective
The Integration Objective |
TAG
Unit 3.3
TAG
Unit 3.4
TAG
Unit 3.5
TAG
Unit 3.6
TAG
Unit 3.7 |
| Appraisal Summary Table |
Transport Appraisal and the New Green Book |
TAG
Unit 2.7 |
| Completing the Appraisal
Summary Table |
The Appraisal Process
Objectives and Problems |
TAG
Unit 2.5
TAG
Unit 2.2 |
| Major Public Transport
Schemes |
Major Scheme Appraisal in Local Transport Plans: Detailed
Guidance on Public Transport and Highway Schemes |
TAG Unit 1.4 |
5. References
Key Documents - General
The following documents are key resources for the assessment
of road schemes:
(DETR, March 2000) GOMMMS Volumes 1 and 2 - now incorporated
into TAG
Highways Agency Design Manual for Roads and Bridges Volume
5 (DMRB)
ODPM (previously DETR) Regional Planning Guidance, Planning
Policy Guidance Note 11 (PPG11)
DfT Guidance on Full Local Transport Plans
Key Documents - Environment
Highways Agency DMRB Volume 11, (Environmental Assessment,
periodically updated)
Key Documents - Safety and Economy
Highways Agency DMRB Volumes 13 (Economic Assessment
of Road Schemes), 14 (Economic Assessment of Road Maintenance)
HETA (Mar 2001) Transport Users Benefit Appraisal User
Manual, TUBA User Guidance with accompanying TUBA software
- TUBA has been developed for the analysis of transport economic
efficiency, for use in the DfT-sponsored Multi-Modal studies.
TEN; HETA (Mar 2001) Transport Economics Note, the primary
source for information on: values of time; values for vehicle
operating costs (fuel and non-fuel); and tax rates.
ICG; HETA (Mar 2001) Interim COBA11 Guidance with accompanying
COBA11 software. The ICG is the primary source for: detailed
accident rates (e.g. for links, junctions, combined links/
junctions); casualties per accident data; values for the avoidance
of accidents. The document also contains data on values of
time and vehicle operating costs, and tax rates for conversion
to market prices (although TEN is the primary source for these
inputs).
Discontinued or Secondary Information
Sources
The following document may be useful as a secondary information
source:
Highways Economics Note 1 (HEN 1, DETR Road Safety Division,
annual). This is a secondary source for accident rates and
unit values. The primary source is ICG.
Discontinued documents that are no longer
relevant are:
Guidance on the New Approach to Appraisal (GNATA, DETR,
1998). This no longer applies to projects within the scope
of this document. In line with a commitment in the Transport
White Paper (DETR, 1998), the new approach to appraisal has
been revised to cover multi-modal appraisal. This multi-modal
version of the new approach to appraisal is presented in GOMMMS;
Highways Economics Note 2 (HEN2, DETR HETA Division, 1994).
The primary source for values of time and vehicle operating
costs is now TEN; and,
URECA software. This is superseded by TUBA.
6. Document
Provenance
This Transport Analysis Guidance (TAG) Unit
is based on S1.3 to 1.9, Chapter 5 and Chapter 6 of Highways
Bridging Document, Applying the Multi-Modal New Approach
to Appraisal to Highway Schemes.
Technical queries and comments on the advice in this note
should be referred to:
Integrated Transport Economics and Appraisal (ITEA) Division
Department for Transport
Great Minster House
Zone 3/08
76 Marsham Street
LONDON SW1P 4DR
Email: itea@dft.gsi.gov.uk
Telephone: 020 7944 6176
Facsimile: 020 7944 2198
Analysts working on specific trunk road investment proposals
in England should refer technical queries to:
Traffic, Safety and Environment Division,
Highway Agency
Room 4/31
St Christopher House
Southwark Street
LONDON
SE1 0TE
E-mail: Assessmentofschemes@highways.gsi.gov.uk
Telephone: 020 7921 4024
Facsimile: 020 7921 4411
|